Project Details

Location Bethel
Project Cost $3.4 Million
Owner Gould Academy
Architect Smith Reuter Lull Architects
Delivery Model Construction Management with Pre-Construction Services

Construction of 18,000 SF Science

Classroom and Laboratory

Contract Awarded: April 16, 2001

Delivery Required: July 2002

Delivery Accomplished: May 2002

Cost: $3,375,715

Change Orders: CM Requested: ($15,603)

Owner Requested: 138,756

Under Budget By: $8,651

Value Engineering: Modest VE, added back most items

CHALLENGES: CM Hired before A/E, MEP Support for labs, campus IT room. Subsurface conditions, rural location