11/13/2019


Check-out the footage News Center Maine captured on World Kindness day during the delivery of our truck load of holiday cheer to the OHI Brewer Area Food Pantry. We at Nickerson & O’Day love supporting our community and giving back when we can. #thankful



October 31, 2019 – 92 Years Later


John Bapst is once again adding a new addition to their facility. Nickerson and O’Day broke ground on Thursday, 10/31/19, to add a new 3.8 million dollar-12,000 SF practice gymnasium and fitness center. The new addition will offer a new, full court basketball gym and improved aerobic/weight training facility which is set to open just in time for the students in the fall of 2020.


October 21, 2019 – 2 months to go!


Work continues at a fevered pace at our $51M Nokomis Junior/Senior High School project in Newport! We turned over the Junior High half of the building in August, just in time for the students, and the High School portion will be winding down in time for Varsity basketball games and the Annual Christmas Show! Classes will begin after the ribbon is cut in early December!


October 15, 2019 – We are back….after 56 years!


Work continues on our $2M Addition and Renovation to the Millinocket Memorial Library – built by us in 1963 and dedicated a week before I was born! Yesterday, we poured and pumped concrete foundations for the addition, all while renovations continue inside! Stay tuned for a Spring, 2020 unveiling!


September 9, 2019 – 25 Years of Building Husson


Nickerson & O’Day took part in welcoming a new era of experiential learning Monday with Husson University’s brand-new Wellness Center. The $4 Million-dollar project, led by Superintendent Bruce Morgan and Vice President Wade Poulton was completed on time and under budget with cost savings to be returned to Husson University. Nickerson & O’Day is proud to have taken part in building a better tomorrow by building a state of the art learning facility for students in the medical field. https://bangordailynews.com/2019/09/09/news/bangor/a-new-building-with-patient-mannequins-helps-husson-double-its-first-year-nursing-class/


July 28, 2019 – Nokomis Middle – High School


July 28, 2019

We are at light speed to complete the first phase of the new $55M Nokomis Middle – High School in Newport! Each day, 150-200 skilled Maine craftsmen help the massive surge in construction, with a late August scheduled completion! The second phase is due in December!


July 28, 2019- Walking in the Footsteps of our Predecessors….56 years later…


July 28, 2019-
This past week, we began the $1.7M Addition and Renovation of the Millinocket Memorial Library! This 9-month effort will make significant upgrades to the structure, accessibility, architecture and function of this important piece of the Katahdin Region.
We built the original library in 1963. We have found lumber in the attic which still bears our name…56 years later!