McLaughlin Science Center, Gould Academy
Project Details
- LocationBethel
- Project Cost$3.4 Million
- OwnerGould Academy
- ArchitectSmith Reuter Lull Architects
- Delivery ModelConstruction Management with Pre-Construction Services
Construction of 18,000 SF Science
Classroom and Laboratory
Contract Awarded: April 16, 2001
Delivery Required: July 2002
Delivery Accomplished: May 2002
Cost: $3,375,715
Change Orders: CM Requested: ($15,603)
Owner Requested: 138,756
Under Budget By: $8,651
Value Engineering: Modest VE, added back most items
CHALLENGES: CM Hired before A/E, MEP Support for labs, campus IT room. Subsurface conditions, rural location